To repair a masonry foundation wall, if a trench is 5 feet wide and 60 feet long, how many cubic yards will be excavated?

Study for the General Contractor License Test. Use flashcards and multiple choice questions, each with hints and explanations. Prepare for success with our structured approach!

To determine the volume of a trench that will be excavated, you can use the formula for volume, which is length × width × depth. In this scenario, the dimensions of the trench are provided as 5 feet in width and 60 feet in length. However, the depth needs to be specified to calculate the total volume accurately.

Assuming that the trench is to be excavated to a standard depth needed for a masonry foundation (such as 3 feet, though this could vary based on local building codes or project specifications), the calculation would be as follows:

  1. Convert the dimensions to cubic feet:
  • Length of the trench: 60 feet

  • Width of the trench: 5 feet

  • Depth of the trench (hypothetical): 3 feet

  1. Calculate the volume in cubic feet:

Volume = Length × Width × Depth

Volume = 60 ft × 5 ft × 3 ft = 900 cubic feet

  1. Convert cubic feet to cubic yards:

Since there are 27 cubic feet in a cubic yard (3 feet x 3 feet x 3 feet),

Volume in cubic yards = 900 cubic feet ÷ 27 cubic feet/cubic yard